Around the solar farm site, the security fencing and internal access tracks are now almost complete. Delivery of the mounting frames for the solar panels is underway and will be carried out until mid-December, after which traffic will ease over the Christmas period. Work on site will be paused from 22/12/2026 until 11/01/2027, whilst site security will remain in place.
During November the team have started piling, which is the installation of the mounting frames using specialised machinery to ensure the frames are securely positioned. This involves driving piles into the ground to create a safe and stable foundation for the panel frames. If you hear some sound coming from the solar farm site, it is likely to be the piling work. The piling is carried out in accordance with the Construction Environmental Management Plan.
Other on-site works in the run-up to the Christmas holidays include the second phase of the archaeological strip mapping, as required by Devon County Council, and the construction of transformer foundations.
In the first week of December, the Distribution Network Operator, National Grid Electricity Distribution (NGED), is planning to undertake some works to their infrastructure which is situated opposite the substation access, adjacent to Bussells. For more information, please contact NGED on 0800 096 3080 between 8am and 5pm Monday to Friday or visit https://customer.nationalgrid.co.uk/contact-us.
The team wish everyone a Merry Christmas and a Happy New Year.
If members of the community have any questions or comments, please contact us via the following channels:
Freepost: FREEPOST THE Y-FACTORY (no stamp or further address details required)
Freephone: 0808 169 8082
Email: consultation@yfactory.co.uk
Website: www.paytherdensolarfarm.co.uk
Thank you for your continued interest in the project.
Marlies Koutstaal Community Engagement Consultant On behalf of the project team